Hydraulic jacking is a construction method that lifts a steel silo from the top down by raising the shell incrementally with synchronized hydraulic jacks. It is preferred over conventional crane assembly because it eliminates高空作业 (high-altitude work), reduces crane dependency, and enables construction of large-diameter silos up to 60 meters with capacities exceeding 100,000 metric tons. This article covers the complete jacking procedure, equipment selection, safety requirements, and quality control protocols.
1. Fundamentals of Hydraulic Jacking for Steel Silos
Figure 1Figure 2Figure 3
1.1 Working Principle
The hydraulic jacking method constructs the silo shell in a horizontal position at ground level, then lifts the entire assembled structure vertically using hydraulic jacks mounted on columns or a central support frame. The process follows a bottom-up assembly sequence: the top ring is welded first, then jacked upward to create space for the next ring below it. Each lift increment typically ranges from 300 mm to 600 mm, matching the width of one shell plate ring.
1.2 System Components
A complete hydraulic jacking system consists of the following core components:
Hydraulic jacks: Center-hole or through-rod type, with individual capacities of 50–200 tons per jack. The number of jacks depends on silo weight; a 40,000-ton grain silo typically requires 20–32 jacks.
High-pressure hydraulic power unit: Electric or diesel-driven pump station delivering 50–70 MPa operating pressure, with flow rates of 4–10 L/min per jack circuit.
Steel lifting columns or truss frame: Structural support that transfers jack reaction forces to the foundation. Columns are typically H-beam sections (H400×400 or larger) with lateral bracing.
Centralized PLC control system: Manages synchronization with displacement sensor accuracy of ±1 mm across all jacks simultaneously.
Lifting lugs and anchor plates: Welded to the inner or outer shell at each jacking point, designed to withstand concentrated loads of 150–300 kN per lug.
2. Pre-Jacking Preparation and Safety Protocols
2.1 Foundation and Base Plate Verification
Before jacking begins, the concrete foundation must achieve at least 70% of its design compressive strength (typically C30/C35 concrete). Base plate anchor bolts are verified for positional tolerance: ±3 mm in plan position and ±2 mm in elevation. The foundation top surface flatness must not exceed 5 mm over any 3-meter span. Grout pads or leveling plates are installed to ensure uniform load transfer.
2.2 Jacking Equipment Calibration
All hydraulic jacks undergo calibration within 30 days prior to use. Each jack is tested at 110% of its rated capacity for a minimum of 5 minutes to verify seal integrity and structural performance. Pressure gauges and displacement sensors are calibrated to ±2% accuracy. The PLC control system is programmed with lift speed parameters: normal operation at 3–5 mm/min, with emergency stop response time under 0.5 seconds.
2.3 Safety Management Plan
A site-specific jacking safety plan must address the following critical risks:
Structural instability: Wind speed monitoring with automatic stop threshold at 10.8 m/s (Beaufort 6). No jacking operations during thunderstorms.
Hydraulic failure: Each jack is equipped with a pilot-operated check valve that locks the cylinder position upon pressure loss. Redundant pump stations provide backup power.
Personnel exclusion: A safety exclusion zone of at least 1.5 times the silo diameter is established around the structure. Only authorized operators enter the jacking area during active lifts.
Emergency procedures: Written contingency plans cover scenarios including jack malfunction, power failure, seismic events, and shell plate buckling. Emergency descent capability must be verified before each lift cycle.
3. Step-by-Step Jacking Execution Process
3.1 Initial Setup and First Ring Assembly
The silo roof and top shell ring (typically 2.0–2.5 m wide) are fully welded at ground level. Lifting lugs are welded to the shell interior at each jacking point location. Jacking columns are erected and plumbed to within 1/500 vertical tolerance. The hydraulic jacks are mounted on column caps, and lifting rods or cables are connected to the shell lugs. A test lift of 50 mm is performed to verify system synchronization and structural response.
3.2 Cyclic Lifting Sequence
Each jacking cycle follows this standardized sequence:
Activate all jacks simultaneously at controlled speed (3–5 mm/min).
Lift the shell by the predetermined increment (typically 1.5–2.0 m per cycle).
Lock jacks in position using mechanical locks or hydraulic check valves.
Weld the next shell ring in the created space below the lifted structure.
Install stiffeners, wind rings, or reinforcement plates as specified.
Perform non-destructive testing (NDT) on all new welds (100% ultrasonic or magnetic particle inspection).
Attach new lifting lugs for the next cycle and release locks to begin the next lift.
A typical cycle duration is 8–12 hours for a 40-meter-diameter silo, including welding and inspection time.
3.3 Final Positioning and Base Fixing
When the silo reaches its design elevation (±15 mm tolerance), the shell is temporarily supported on steel blocking. Anchor bolts are inserted through base plate holes and torqued to specified values (typically 200–400 N·m depending on bolt grade and diameter). The hydraulic jacks are gradually lowered in synchronized stages of 10 mm increments, transferring the full structure weight to the foundation. Final shell verticality is verified: maximum allowable deviation is H/500 (where H is silo height), not exceeding 50 mm total.
Engineering Tip: For silos exceeding 30 meters in diameter, install at least 4 tilt sensors (inclinometers) on the shell circumference at 90° spacing. Real-time monitoring detects asymmetric loading before visible deformation occurs. Alarm threshold: 0.5° deviation from vertical; emergency stop threshold: 1.0°.
4. Technical Specifications and Equipment Selection
4.1 Jack Capacity Calculation
The required jack capacity is determined by the maximum lifted weight at any construction stage. The calculation formula is:
Individual Jack Capacity = (Total Weight × Safety Factor) / Number of Jacks
Where total weight includes shell plates, stiffeners, roof structure, and temporary loads (welding equipment, personnel, wind loads). The dynamic safety factor shall not be less than 2.0. For example, a silo with a maximum lifted weight of 800 tons using 24 jacks requires individual jack capacity of (800 × 2.0) / 24 = 66.7 tons minimum—select 80-ton jacks for standard availability.
4.2 Lifting Speed and Synchronization
Maximum lifting speed during normal operation shall not exceed 6 mm/min. The PLC system maintains synchronization accuracy of ±2 mm between adjacent jacks and ±5 mm across the full circumference. Lift speed is reduced to 1–2 mm/min during the final 100 mm of each cycle for precise positioning. Total lift time for a 1.5-meter increment at 4 mm/min is approximately 6 hours, not including welding and inspection time.
5. Quality Control and Inspection During Jacking
5.1 Dimensional Monitoring
Shell geometry is checked after each jacking cycle using total station surveying equipment. Key measurements include:
Verticality: measured at 4 cardinal points, recorded every 5 meters of lift height.
Circumference: verified against design tolerance of ±D/500 (where D is nominal diameter).
Shell plate alignment: butt weld offset not exceeding 1.5 mm for plates up to 12 mm thick, 2.0 mm for thicker plates.
Ovality: difference between maximum and minimum diameters shall not exceed D/300.
5.2 Weld Quality Assurance
All shell welds are subject to the following inspection regime:
Visual inspection (VT): 100% of all welds before and after each jacking cycle.
Ultrasonic testing (UT): 100% of vertical and circumferential butt welds, performed by Level II certified technicians per recognized standards.
Magnetic particle inspection (MT): Applied to lifting lug welds and high-stress connection details.
Hardness testing: Performed on 5% of weld joints to verify heat-affected zone hardness does not exceed 380 HV10 for carbon steel silos.
6. Post-Jacking Procedures and Commissioning
6.1 Base Grouting and Anchoring
After the silo is fully lowered onto its foundation, the gap between base plate and foundation (typically 30–50 mm) is filled with non-shrink grout (compressive strength ≥50 MPa). Grouting is performed in continuous pours from one side to prevent air entrapment. Anchor bolts are retorqued after 72 hours of grout curing. Final bolt tension is verified using calibrated torque wrenches or direct tension indicators.